WeHo Design District Streetscape Project

WeHo Design District Streetscape Project
Phase 2A: Complete; Phase 2B (undergrounding): Begins July 2024; Phase 2C (streetscape): Approx. 2026 Phase 1 (streetscape): Complete Phase 3A (undergrounding): Approx 2025; Phase 3B (streetscape): Approx. 2026

Phase 2A: Complete; Phase 2B (undergrounding): Begins July 2024; Phase 2C (streetscape): Approx. 2026

Phase 2A - Undergrounding (Melrose west)
Complete 2023

Phase 2B - Undergrounding (Almont + La Peer)
Construction begins June 2024

Phase 2C - Streetscape (Melrose west, Almont, La Peer, Robertson north)
Construction approx. 2026

Phase 1 (streetscape): Complete

Phase 1 - Streetscape (Melrose east)
Complete 2024 with exception of Weaver's Walk

Phase 3A (undergrounding): Approx 2025; Phase 3B (streetscape): Approx. 2026

Phase 3A - Undergrounding (Beverly, Robertson)
Construction approx. 2025

Phase 3B - Streetscape (Beverly, Robertson)
Construction approx. 2026