Phase 2B – Undergrounding (Almont + La Peer)
starts July 2024

Latest Construction Notice

Construction Notice: Directional Boring Operation on Santa Monica Blvd

Construction Notice: Directional Boring Operation on Santa Monica Blvd

CONSTRUCTION DATE & TIME:

  • Approx. August 28 – September 11, 2024
  • Monday – Friday, 9:00AM – 4:00PM

WHAT TO EXPECT:

  • For approximately one week, construction will take place on Santa Monica Blvd. with construction area spanning onto N. Almont Dr.
  • Construction crew and equipment on site.
  • Moderate noise from machinery.

TRAFFIC FLOW:

  • Traffic will continue to flow north and south on N Almont Dr. with one lane in each direction.
  • Eastbound traffic on Santa Monica Bld. will merge into one lane starting from Doheny Dr.
  • Please obey traffic signs.
  • No right turns allowed from N Almont Dr. onto Santa Monica Blvd.

TRAFFIC CONES:

  • Cones will be placed around the work zone to identify the construction area, maintain safety, and guide vehicles.
  • Local and customer vehicles will be permitted by flagger to enter driveway and private property unless notified in advance.
  • Restrictions on city meters must still be obeyed.

PARKING:

  • Parking shall be temporarily restricted at some city parking meters to provide access to the work zone.
  • Specific date and time of parking restrictions will be posted on each individual meter.

DRIVEWAYS:

  • Driveways inside the construction zone will be granted access by crew as necessary.
  • Crew will be onsite to guide vehicles into and out of roadway and driveways in the construction zone.

Want to receive notifications about the WeHo Design District Streetscape project? Get updates by email here.

Community Updates

Project updates for business and residents, including outreach meeting recordings and materials.

Utility Undergrounding on Almont + La Peer Project Update and Look Ahead

Recording for West Hollywood Undergrounding on Almont + La Peer Construction Outreach Meeting

Construction Notices

Construction notices and alerts for businesses and residents.

Construction Notice: Directional Boring Operation on Santa Monica Blvd

Construction Notice: Construction Activities on Almont: August 19 – 27, 2024

Join Our Mailing List

Be first to know the latest news on construction.

Need Assistance?

i

Public Comment Form

We want to hear from you!

WeHo Design District Melrose Streetscape Final Construction Activities

We can’t wait to celebrate the WeHo Design District’s 75th anniversary after Melrose Avenue Streetscape’s final construction activities are completed. Check out the final timeline and projects features.

Project Benefits

  • Pedestrian and bicycle safety improvements

  • New street pavements and sidewalks

  • Distinctive trees and landscaping

  • Upgraded street furniture and energy efficient streetlights

  • Smart city infrastructure installation

  • Utility undergrounding

  • Creation of new public gathering places with integrated public art

  • Electric vehicle charging stations, bus shelter upgrades, pedestrian safety crossing roadway lighting system, and WiFi system

WeHo Design District Streetscape Project Map

WeHo Design District Streetscape Project

WeHo Design District Streetscape Project
Phase 2A: Complete; Phase 2B (undergrounding): Begins July 2024; Phase 2C (streetscape): Approx. 2026 Phase 1 (streetscape): Complete Phase 3A (undergrounding): Approx 2025; Phase 3B (streetscape): Approx. 2026

Phase 2A: Complete; Phase 2B (undergrounding): Begins July 2024; Phase 2C (streetscape): Approx. 2026

Phase 2A - Undergrounding (Melrose west)
Complete 2023

Phase 2B - Undergrounding (Almont + La Peer)
Construction begins June 2024

Phase 2C - Streetscape (Melrose west, Almont, La Peer, Robertson north)
Construction approx. 2026

Phase 1 (streetscape): Complete

Phase 1 - Streetscape (Melrose east)
Complete 2024 with exception of Weaver's Walk

Phase 3A (undergrounding): Approx 2025; Phase 3B (streetscape): Approx. 2026

Phase 3A - Undergrounding (Beverly, Robertson)
Construction approx. 2025

Phase 3B - Streetscape (Beverly, Robertson)
Construction approx. 2026