Melrose Construction Alert: Concrete Pours Between N San Vicente and Westbourne Dr
A color-coded map of concrete pour locations and corresponding dates is avaialble. The concrete will be poured in segments to accommodate the large area and allow for pedestrian access. Please note, additional pours will be scheduled for areas in gray, including the decorative concrete bands and the Norwich Gathering Space (block between Norwich and Huntley Ave).
These dates and locations are approximate and may adjust based on concrete material availability, crews, and speed of work.
If you have any questions, please feel free to reach out to: Jenelle Saunders Public Outreach Manager (WehoDesignDistrictStreetscape@bergcm.com)
The contractor is scheduled to begin sidewalk pours on Monday, August 14, 2023. The concrete will be poured in segments to accommodate the large area and allow for pedestrian access. There are five days of planned pours from San Vicente and Norwich Dr.:
- Monday, August 14, 2023
- Tuesday, August 15, 2023
- Wednesday, August 16, 2023
- Monday, August 21, 2023
- Tuesday, August 22, 2023
And two days (additional days to be added) of planned pours from Huntley Dr to Westbourne Dr.:
- Tuesday, August 15, 2023 (bus pad in roadway)
- Wednesday, August 23, 2023