Construction Alert: LADWP Work on Huntley Dr and W Knoll (Courtesy Notice)
Project Phase: Phase 1 - Streetscape (Melrose east)
Date of Notice: August 22, 2023
This is a courtesy post about a project being constructed by LADWP (not related to the Streetscape Project).
This notice is to inform you of the preliminary schedule for a Mainline Project being constructed by Los Angeles Department of Water and Power (LADWP).
LADWP will be beginning a Mainline Project on Huntley Dr. and W Knoll Dr. starting Wednesday, August 23, 2023. The project will start on Huntley Dr. and then move to W Knoll Dr. with a duration of approximately 3 months.
The schedule includes work Monday – Saturday from 8AM to 4PM.
Start Date: Wednesday, August 23, 2023 starting on Huntley Dr.
Location:
- Huntley Dr. from Melrose Ave to Sherwood
- W Knoll from Melrose Ave to Santa Monica Blvd.
Duration:
- Approximately 3 months
Schedule
- Monday – Saturday, 8AM – 4PM