Utility Undergrounding on Almont Dr + La Peer Dr

Date of Notice: June 28, 2024

WORK ACTIVITIES & SCHEDULE:

Construction activities including asphalt sawcutting, demolition, potholing, and plating will take place in the roadway between the addresses of 632 and 648 N Almont Dr. Traffic control cones will extend from 614 to 648 N Almont Dr. to identify the construction area, maintain safety, and guide vehicles.

CONSTRUCTION DATE & TIME:

  • Monday, July 1, to Wednesday, July 3, 2024 8:00AM – 5:00PM

WHAT TO EXPECT:

  • Construction crew and equipment on site.
  • Moderate noise from machinery.

TRAFFIC FLOW:

  • Traffic will continue to flow north and south on N Almont Dr. with one lane in each direction.
  • Left and right turns onto/from Santa Monica Blvd. will be permitted.

TRAFFIC CONES:

  • Cones will be placed around the construction zone to identify the construction area, maintain safety, and guide vehicles.

DRIVEWAYS:

  • Driveways inside the traffic control (cone) zone will remain open and accessible.
  • Driveways inside the construction zone will be granted access by crew as necessary.
  • Crew will be onsite to guide vehicles into and out of driveways in the construction zone.

PARKING:

  • Parking shall be temporarily removed at some parking meters to provide access to the work zone.
  • Specific date and time of parking removals will be posted on each individual meter.

Please be aware that construction is a dynamic process and adjustments may occur to ensure efficiency and safety.

Questions or Concerns?

Image showing map of Work Activities & Schedule for Almont Dr.