Biweekly Business Outreach Meeting No. 4 – Thursday, October 13, 2022
Project Phase:
Stage 5: Melrose Ave from San Vicente to Croft Ave (beginning on south side)
Why Stage 5?
- SCE can move quicker to finish work in ongoing construction stages
- SCE given approval to work day & night
- Stage 1 sidewalks poured by Thanksgiving
- Minimize the number of businesses/people impacted during the holiday season
- Metered parking restored in a majority of areas in Stages 1 – 4 (north and south side of Melrose)