Biweekly Business Outreach Meeting No. 4 – Thursday, October 13, 2022

Stage 5: Melrose Ave from San Vicente to Croft Ave (beginning on south side)

Why Stage 5?

  • SCE can move quicker to finish work in ongoing construction stages
  • SCE given approval to work day & night
  • Stage 1 sidewalks poured by Thanksgiving
  • Minimize the number of businesses/people impacted during the holiday season
  • Metered parking restored in a majority of areas in Stages 1 – 4 (north and south side of Melrose)