Beginning August 8 Westmount North Side Closure & LADWP Westmount Street Closure
Project Phase: Phase 1 - Streetscape (Melrose east)
Date of Notice: August 5, 2022
Westmount North Side Closure
Westmount Dr. will be closed on the north side of Melrose Ave from Monday, August 8, 2022 through Monday, August 15, 2022, from approximately 8:00am to 5:00pm, remaining open during the weekend, August 13 – 14, 2022.
- Intersection will be opened and traffic restored at the end of each working day.
- Intersection will be open throughout the weekend.
- Eastbound and westbound traffic on Melrose Ave will continue.
SCHEDULE
- Monday, August 8, 2022; 8AM – 5PM
- Tuesday, August 9, 2022; 8AM – 5PM
- Wednesday, August 10; 8AM – 5PM
- Thursday, August 11; 8AM – 4PM
- Friday, August 12; 8AM – 4PM
- Monday, August 15; 8AM – 4PM
LADWP Westmount Street Closure
LADWP will be conducting waterline relocations between Melrose Ave and Sherwood Dr. from Monday, August 8, 2022 through approximately Friday, September 16, 2022.
- Parking will be restricted adjacent to the working area through project progression.
- Local/residential access only.
SCHEDULE
- August 8 – September 16, 2022
- Monday – Friday, 8AM – 5PM
Please sign up for project alerts by joining the email list.