Due to rain and wet roadway conditions, Stage 4 mobilization and Stage 5 demobilization have been rescheduled to Monday, April 3 and Tuesday, April 4, 2023.

On April 3, 2023, the traffic signals at Melrose Ave and La Cienega Blvd will be temporarily disabled between 9:00am – 3:00pm in order to remove the signal poles on the northeast and southeast corners. There will be traffic control officers on site to guide vehicles and pedestrians through the intersection.

Please see work schedule and activities below:

Monday, April 3, 2023: Traffic Signal Work at Melrose and La Cienega

  • Signals temporarily inoperative between 9AM – 3PM
  • Traffic control officers will direct traffic while signals are out

Monday, April 3rd and Tuesday, April 4th, 2023: Mobilization into Stage 4

Stage 5 Demobilization

Barricade removal and lane striping: April 3 & 4, 2023

  • Parking restored: April 4, 2023
  • Stage 4 Mobilization

Parking removed and traffic control set up: April 3 & 4, 2023

  • Saw-cutting (noise): April 5, 2023
  • Begin tree removals: April 5, 2023

We encourage you to attend our next Business Focused Outreach Meeting, every Thursday at 2pm via Zoom. These meetings focus on schedule updates, impacts, and providing opportunities for businesses to ask questions and speak directly with the project team.

Register in advance for this meeting: https://us02web.zoom.us/meeting/register/tZUrduysrjMsGNWaQ_WUJGjU70DigZ1akVJH

After registering, you will receive a confirmation email containing information about joining the meeting.