Construction Notice & Meeting Invitation: Street Closure for Vault Installation on Almont Dr.
The Almont & La Peer Undergrounding Project Team would like to cordially invite you to attend bi-weekly progress outreach meetings starting on July 11, 2024, as well as provide details on next week’s planned closure of N Almont Dr. Please see information below and attached for more details.
Construction Notice Details:
The preparation and installation of utility vaults on N Almont Dr. will take place from Monday, July 8 through Friday, July 12, 2024. To ensure the safety and efficiency of the work, road closures and lane closures will be in effect. These closures are necessary to provide crew access to the construction area, accommodate large cranes, and safely install equipment.
Construction Date and Time:
Monday, July 8 to Friday, July 12, 2024
8:00AM – 5:00PM
ROAD CLOSURE: July 8 to July 11, 2024
ONE LANE CLOSURE: July 12, 2024
Traffic Flow During Closure:
Local access only. No through traffic.
No access to or from Santa Monica Blvd to N Almont Dr.
Vehicles traveling north on N Almont Dr. from Melrose Ave. will be required to make a U-Turn at road closure.
Outreach Meeting Details:
Please join the project team for bi-weekly outreach meetings where we will provide updates on the Design District Undergrounding of Almont + La Peer. During these meetings, we will discuss construction progress, schedule updates, and address any questions.
When: Jul 11, 2024 02:00 PM
Register in advance for this meeting: https://us02web.zoom.us/meeting/register/tZMud-yhqz8iGNBDgfIYciBOEKAty3c2RU7f
After registering, you will receive a confirmation email containing information about joining the meeting. Your participation is valuable to us, and we look forward to sharing the latest developments and hearing your feedback.