Asphalt repairs on Melrose Avenue between San Vicente Blvd and Croft Ave will take place starting November 4, 2024. Construction activities will include grinding and paving various areas along the north side of Melrose Ave on night one, and various areas on the
south side of Melrose Ave on night two. Night three entails traffic lane striping layout with striping installation approximately one week later. Parking restrictions will be implemented and traffic lanes will be modified in the work area.

Planned activities include:

  • Night 1: Grinding and paving on the north side of Melrose Ave.
  • Night 2: Grinding and paving on the south side of Melrose Ave.
    • Note: Equipment used during these first two nights will generate moderate noise.
  • Night 3: Layout for traffic lane striping
  • Night 4 (approx. one week later): Final striping installation.

WHAT TO EXPECT

  • Night work from 9PM – 6AM
  • Parking restrictions with durations posted on individual meters.
  • Traffic lane modifications.
  • Noise from asphalt grinding.
  • Construction machinery and crews working at night.

To ensure safety and allow access to the work area, parking restrictions and modified traffic lanes will be in effect. Please see attached construction notice for more details.

We appreciate your cooperation and understanding as we work to improve our roads.

Flyer with construction notice information