For the duration of this work (9/19 – 9/30), pedestrian traffic will be routed south of the sidewalk in a delineated pathway along the roadway. Access pathways to business entrances will be delineated and maintained at all times, with the exception of those businesses identified in the attached Access Worksheet during concrete pours on specific days.
In summary:
- Sept 19: Pedestrian access will be rerouted in the delineated path in the roadway.
- Sept 19: Band forms will be placed
- Sept 20: Bands will be poured.
- Sept 21-22: Concrete sidewalks will be poured.
- Sept 26-28: Concrete sidewalks will be poured.
- Sept 29-30: Temporary Asphalt will be placed. During these activities, access to affected business entrances will only be restricted for a short time period.
MELROSE AVE STAGE 3 SIDEWALK POUR SCHEDULE
September 19 – 30, 2022
Sept. 19, 2022 – Form Bands
Westbourne to La Cienega: All business entrances will remain accessible to public. Pedestrian traffic will be routed into street and access to business entrances will be delineated and maintained. If any business access is temporarily restricted, that business will be contacted by our public outreach team. Each band form is a quick process to install.
Sept. 20, 2022 – Pour Bands
Westbourne to La Cienega: All business access will remain available. If any access is restricted, it will be for a short time period.
Sept. 21, 2022 – Pour Sidewalk
Westbourne to Westmount: Access to business entrances will be maintained.
Sept. 22, 2022 – Pour Sidewalk
Westmount to Knoll: Access will be restricted for the following business entrance(s): None
Sept. 26, 2022 – Pour Sidewalk
Westmount to La Cienega: Access will be restricted for the following business entrance(s): State and Liberty, Cutler and Gross
Sept. 27, 2022 – Pour Sidewalk
Westbourne to Westmount; Knoll to La Cienega: Access will be restricted for the following business entrance(s): Our Place, Anna Sheffield
Sept. 28, 2022 – Pour Sidewalk
Westmount to Knoll: Access will be restricted for the following business entrance(s): Glossier
Sept. 29, 2022 – Place Temp AC
Westbourne to La Cienega: Access will be temporarily restricted for the following business entrance(s): HOKA, Alfred Alice and Olivia, SOL
Sept. 30, 2022 – Place Temp AC
Westbourne to La Cienega: Access will be temporarily restricted for the following business entrance(s): HOKA, Alfred, Alice and Olivia, SOL