SCE Work Locations (East of San Vicente) October 24 – 27, 2022
Project Phase: Phase 1 - Streetscape (Melrose east)
Date of Notice: October 24, 2022
Southern California Edison will be working in vaults and pulling cable on Melrose Ave. Parking will be temporarily removed in the work zone to provide access and maintain safety.
WORK SCHEDULE
Mon., Oct. 24, 2022
8625 Melrose
8AM – 5PM (day work)
8625 Melrose
8PM – 5AM (night work)
Tues., Oct. 25, 2022
8619 Melrose
8AM – 5PM (day work)
8625 Melrose & 8575 Melrose
8PM – 5AM (night work)
Wed., Oct. 26, 2022
8625 Melrose & 8575 Melrose
8AM – 5PM (day work)
Thurs., Oct. 27, 2022
8625, 8619 & 8575 Melrose
8PM – 5AM (night work)