Updated Schedule: Temporary Asphalt and Artificial Turf Installation (updated)

Date of Notice: May 28, 2024

The Weaver’s Walk temporary turf installation has been scheduled for the following dates:

  • June 5 & 6, 2024: Compaction of loose base rock work will commence and will take two days to complete.
    June 7 – 21, 2024: Crews will install artificial turf in designated areas. Work is expected to take approximately two weeks to complete.
Updated Schedule: Temporary Asphalt and Artificial Turf Installation