Tomorrow, October 1, 2024, construction to grind and pave the roadway on Almont Dr and Santa Monica Blvd will take place. Traffic will continue to flow with intermittent lane closures and vehicular traffic shifting throughout the day in order provide access to the work zone. Moderate noise is expected during asphalt grinding.
Restrictions on city meters must still be obeyed. Specific date and time of parking restrictions will be posted on each individual meter.
Please see PDF notice attached for the full map and construction activity details.
CONSTRUCTION DATE AND TIME:
- Tuesday, October 1, 2024
- 8:00AM – 5:00PM
WHAT TO EXPECT:
- Roadway asphalt grinding and asphalt paving on Almont Dr. and Santa Monica Blvd.
- Intermittent lane closures with traffic shifted throughout the day depending on work zone location.
- Moderate noise during grinding from machinery.
The City hosts virtual, project progress meetings every other week to provide schedule and work activity updates, as well as to answer any questions you may have. Please join us for our next meeting:
Next Progress Meeting: October 3, 2024 at 2pm – sign up for the recurring zoom meeting here!